REGAL RESOURCES LTD : DISCLOSURE ON DISRUPTION OF OPERATIONS

• Damage detected in rotor and fan of one 10 MW turbine at manufacturing facility in Bihar, commissioned May 26, 2026. • Repair expected to take approximately 35 days, with recommissioning by September 30, 2026. • Estimated repair cost is ₹90 lakhs; loss/damage covered by insurance. • Production at the 825 TPD facility was running at 50% capacity; other operations remain unaffected. • Company has requisite stock to service existing and ongoing orders. Impact: Neutral (Temporary disruption to one turbine, insurance coverage in place, and sufficient stock to meet orders.)