22-Sept-2026 12:08:54
BORORENEWExpansion
BOROSIL RENEWABLES : EXPANDS CAPACITY AT BHARUCH
• Board approved revised project cost estimate of up to ₹1100 crores for expansion project. • Commissioning timeline updated to end of March 2027, delayed from December 2026. • Expansion project scope increased, leading to additional cost outlay of ₹150 crores. • Additional costs to be met through internal funds without increasing borrowings. • Project update includes setting up of two 300 TPD furnaces (SG-4 & SG-5) at Bharuch. • Original investment envisaged was ₹950 crores for 600 TPD capacity addition.
Borosil Renewables Ltd