24-Sept-2026 12:47:18
INTERARCHExpansion
INTERARCH BUILDING SOLUTIONS LTD : STARTS COMMERCIAL PRODUCTION AT ANDHRA PRADESH UNIT 2
• Company commenced commercial production at its newly established manufacturing facility located at Andhra Pradesh. • This marks the commencement of commercial production of Andhra Pradesh Unit 2 Phase-1 (HSS). • The total installed manufacturing capacity has increased from 221,000 MT to 245,000 MT with effect from 24th September'2026. • Existing capacity utilisation was 70% prior to this addition. • The capacity addition of 24,000 MT was completed between Q2-FY26 and Q2-FY27. • Investment required was ₹80 Cr (excluding land), financed through internal accruals.
Interarch Building Solutions Limited
Open attachment