ACME SOLAR HOLDINGS LTD : EXPANSION OF BESS CAPACITY IN RAJASTHAN
• ACME Solar has operationalized additional cumulative BESS capacity of 107.36 MW / 437.49 MWh in Rajasthan. • This capacity has been commissioned across two key projects, with commissioning achieved on September 30, 2026, and Commercial Operation Date (COD) on October 02, 2026. • The first phase of a FDRE Project at Neemri village has commissioned 53.73 MW / 222.969 MWh. • Phase III of an Assured Peak Power Project at Kelan village has commissioned another 53.63 MW / 214.52 MWh. • Following these milestones, the total operational BESS capacity of ACME Solar stands at 4.96 GWh. Impact: Expansion of renewable energy capacity in Rajasthan.