CEIGALL : RECEIVES COMPLETION CERTIFICATE FOR RS 1,659.84 CR DELHI-SAHARANPUR HIGHWAY PROJECT
• Completion Certificate received for 16.85-km, six-lane, access-controlled stretch of NH-709B from Delhi/UP border to EPE junction • Project revised estimated cost ₹1,659.84 Cr; part of Economic Corridor under Phase I of Bharatmala Pariyojana • Highway declared fit for operation with effect from September 12, 2024; certificate dated October 12, 2026 • Ceigall to undertake operation & maintenance of the stretch at ₹2.88 Cr per annum plus escalation • Project executed jointly with Gayatri Projects Limited for NHAI; awarded April 16, 2022, with extended completion date August 15, 2024