BHANSALI ENGINEERING Q2 FY27 ; ₹200 CR ABS CAPACITY EXPANSION DELAYED 🔴

• Company is expanding ABS production capacity from 75,000 TPA to 1,00,000 TPA, an increase of 33%. • Estimated project cost stands at ₹200 crore. • Project completion delayed from September 2026 to March 2027. • Imported equipment deliveries delayed due to shipping container shortages and global supply-chain disruptions. • Foreign suppliers' service engineers are unable to confirm commissioning schedules. • Reactor delivery delayed and now expected in November 2026. • Management is revising shutdown and installation schedules to minimise production losses. • Management remains confident of completing the expansion by March 2027.