23-Oct-2026 20:34:51

ACMESOLARExpansion

ACMESOLAR : COMMISSIONS 17.91 MW/74.323 MWH BESS CAPACITY IN RAJASTHAN

• Additionally commissioned BESS component of 17.91 MW/74.323 MWh at FDRE project in Chittorgarh, Rajasthan • Capacity is part of the 250 MW/1069 MWh (discharge capacity) FDRE project at Neemri village, Rawatbhata tehsil • Commercial operation date for the new capacity set at October 25, 2026 • Commissioning done through wholly owned subsidiary ACME Sigma Urja Private Limited • Cumulative commissioned BESS capacity of ACME Sigma Urja now at 71.640 MW/297.292 MWh

Acme Solar Holdings Limited