12-Nov-2026 15:52:36

NCLINDExpansion

NCL INDUSTRIES : APPROVES 130 MW SOLAR-WIND PROJECT WORTH RS 987.17 CR

• Board approved Phase II & III, the balance 80 MW, at an estimated project cost of ₹595.17 Cr • Phase I of 50 MW was approved in April 2026 at ₹392 Cr; aggregate 130 MW project cost now ₹987.17 Cr • Project located at Tuticorin, Tamil Nadu; to be funded through a mix of debt and internal accruals • CTUIL has granted final connectivity/transmission access; scheduled commissioning February 2028 • Rationale is to meet captive power requirements and sell surplus through power exchanges and third-party PPAs • Board also gave in-principle approval to approach the Odisha government for a proposed cement plant; no land allotted or binding agreement executed yet

NCL Industries Limited