18-Nov-2026 07:41:23

EXIDEINDGeneral news

EXIDE : DILUTES STAKE IN ULRIC RENEWABLES TO 26.07%

• Exide has diluted its equity shareholding in Ulric Renewables from 39.08% to 26.07% • Captive wind project of 10.5 MW at Jath, Maharashtra for the Maharashtra factories could not be commissioned within the scheduled commencement date • Dilution done as per mutually agreed terms between Ulric, Exide and Cleantech Solar India OA 2 Pte Ltd, including amendment and settlement documentation • 8.4 MW captive wind project for the Hosur facility, Tamil Nadu remains operational and Ulric will continue supplying power to Hosur • Original investment covered captive wind projects aggregating 18.9 MW for the Tamil Nadu and Maharashtra plants Impact: Neutral (Lower stake follows delay in the 10.5 MW Jath project; operational Hosur supply arrangement and no consideration disclosed)

Exide Industries Ltd