GLENExpansion

GLEN : COMMERCIAL PRODUCTION TIMELINE EXTENDED AGAIN

• Commercial production now expected by Q4 FY 2026-27, extended from Q3 FY 2026-27; originally Q4 FY 2025-26 as per RHP • All regulatory approvals now in place — WBPCB consent to establish, Fire NOC/FSR, WBSEDCL power sanction and building plan sanction from Zila Parishad • Land conversion to industrial completed, land filling done; PEB contract awarded and erection commenced, piling complete with foundation likely by end-October 2026 • Orders placed for all plant and machinery and utility equipment • Delay attributed to West Bengal SIR and election-related building plan approval, excessive rain and delayed power sanction • IPO proceeds fully utilised, no unutilised proceeds remain

Glen Industries Ltd