20-Nov-2026 21:54:25
ACMESOLARExpansion
ACME SOLAR : COMMISSIONS 35.81 MW BESS CAPACITY AT CHITTORGARH PROJECT
• Wholly-owned subsidiary ACME Sigma Urja commissioned 35.81 MW / 148.645 MWh discharge capacity of the BESS component • Part of the 50 MW / 209 MWh BESS for the TATA FDRE Power Project at Neemri, Rawatbhata, Chittorgarh, Rajasthan • Commissioned on November 20, 2026; commercial operation date set for November 22, 2026 • Only the BESS component has been commissioned so far; PPA signed with The Tata Power Company Limited
Acme Solar Holdings Limited
Open attachment