26-Nov-2026 08:30:57

ACMESOLARExpansion

ACME SOLAR : COMMISSIONS 63.78 MW BESS CAPACITY AT JAISALMER

• Wholly-owned subsidiary ACME Hybrid Urja commissioned 63.78 MW / 255.120 MWh discharge capacity (installed 63.78 MW / 300.00 MWh) of the BESS component • Part of the 280 MW / 1120 MWh BESS portion of the NHPC FDRE power project at Mehar Nagar, Pokaran, Jaisalmer, Rajasthan • Only the BESS component has been commissioned so far; commercial operation date for the same is November 27, 2026 • Power purchase agreement for the project is signed with NHPC Limited

Acme Solar Holdings Limited

Open attachment